ARCHIVE – CONSTRUCTION UPDATES
WEEKLY UPDATES – Archived
6/17/2020
We apologize for all the dust! Workers continue to excavate for sewer, water connections, and walkways. The first pour of concrete for walkways has begun.
4/28/2020
Curbing completed. Construction continues despite campus closure.
2/3/2020
Due to a change order, the project is temporarily on hold. Construction will resume when materials are received.
1/6/2020
Blocked off parking stalls (10-12) in the front parking lot (Jan. 6-8) due to the installation of a fire hydrant for the new building.
12/2/2019
Site grading and pouring cement in trench along the Music Building.
10/25/2019
Due to a change order, the project is temporarily on hold. Construction will resume when materials are received.
10/11/2019 to 10/21/2019
- Site Grading – will include bringing in and moving large amounts of dirt.
Week of 9/23/2019
- Continuing to bury conduit
- Digging to tie-in to water and electric resources near cafeteria
Week of 9/16/2019
- Clearing area to install waterlines
- Footing and excavation preparation
Week of 9/9/2019
- Waterline trenching begins
- Electrical conduit installation
Week of 9/3/2019
- Drilling and probing (footing excavation)
- Cap and install new waterlines
Week of 8/26/2019
- Finish 8-foot barrier surrounding the worksite.
- Trenching and digging for conduit 8/26/2019 – 8/30/2019
- Road work will be conducted. Please observe safety signs.